Dana Library Transformation Project

And the Constructing Goes on.

There are no major construction announcements for this or the upcoming week. Work continues on the foundational/preparatory needs for the building the addition and building out the third floor.

The exterior work will concern the elevator shaft and building foundation. They will begin pouring the concrete for the new elevator shaft starting on Monday, May 27th. Concurrently, work on the footings and foundation of the building for the new addition will also be happening.

The interior work focuses on the third floor. This week the focus was on establishing the necessary connections for the third floor plumbing; this will require some activity on the second floor as well. The third floor build out progresses from laying down tracks to installing the framing for the new walls.